Answer first: The ISTS full form is the Inter-State Transmission System — the high-voltage network that carries electricity between states, and within a state on lines built or controlled by the Central Transmission Utility. ISTS charges are set under regulations of the Central Electricity Regulatory Commission and paid mainly by the entities that draw power from the network. Since 2016, solar and later wind projects have been able to earn a waiver of these charges for 25 years. The waiver is now being phased down in annual steps, and for projects commissioned between 1 July 2026 and 30 June 2027 it stands at 50 per cent. |
Transmission rarely makes it into a boardroom conversation about electricity, yet it sits inside every unit a business buys. When the power comes from a generator in another state, the cost of moving it across the national grid is one of the lines that decides whether a renewable supply arrangement works.
That is why the ISTS waiver has mattered so much. For close to a decade it removed inter-state transmission charges from new solar and wind projects, and it is now stepping down to zero on a published schedule. This page explains what the ISTS is, who runs it, how its charges are set and shared, and exactly where the waiver stands — with the instrument and the date behind each point.
ISTS stands for Inter-State Transmission System. The term comes from the Electricity Act, 2003, which defines it by function rather than by voltage.
|
Definition — inter-State transmission system (Electricity Act, 2003, Section 2(36)): “‘inter-State transmission system’ includes— (i) any system for the conveyance of electricity by means of main transmission line from the territory of one State to another State; (ii) the conveyance of electricity across the territory of an intervening State as well as conveyance within the State which is incidental to such inter-State transmission of electricity; (iii) the transmission of electricity within the territory of a State on a system built, owned, operated, maintained or controlled by a Central Transmission Utility.” |
Three things follow from that definition. First, a line does not have to cross a state border to be part of the ISTS — a line inside one state counts if it is incidental to inter-state flow or is built or controlled by the Central Transmission Utility. Second, everything else is intra-state: the Act defines an intra-state transmission system simply as any transmission system other than an inter-State one. Third, the difference decides which regulator sets the charge. Inter-state transmission is regulated by the Central Electricity Regulatory Commission (CERC); intra-state transmission by each State Commission.
The ISTS is a shared piece of national infrastructure, and each part of it has a named owner. For the wider picture of the institutions involved, see how India's power sector is structured.
|
Role |
Who holds it |
|
Planning and coordination |
The Central Transmission Utility of India Ltd (CTUIL), designated as the Central Transmission Utility with effect from 1 April 2021. It is a wholly owned subsidiary of POWERGRID, set up as a separate company for the purpose. |
|
Building and owning lines |
Transmission licensees. POWERGRID remains the largest owner-operator. Many new projects are awarded through tariff-based competitive bidding, to both POWERGRID and private developers. |
|
Billing and collection |
CTUIL raises transmission bills, collects the charges and disburses them to the licensees. |
|
Computing each user's share |
The Implementing Agency — the National Load Despatch Centre, run by Grid Controller of India (Grid-India), or another agency the Commission designates. |
|
Setting the rules and the charges |
CERC, through its regulations on sharing of transmission charges and on connectivity and network access. |
The network these institutions run has grown quickly. Transmission lines at 220 kV and above crossed five lakh circuit kilometres on 14 January 2026, and 84 transmission projects had been awarded through tariff-based competitive bidding by the end of 2025, 74 of them commissioned. That build-out is what has allowed renewable capacity in resource-rich states to reach buyers elsewhere.
ISTS charges are the regulated charges that recover the cost of building and running the inter-state network. The licensees' revenue is fixed by CERC; the question the regulations answer is how that fixed total is divided among the network's users.
The current method is set by the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020, notified on 4 May 2020 and in effect from 1 November 2020. They have been amended four times, most recently on 26 June 2025. Under them, the total is built up from four components:
|
Component |
What it covers |
|
National Component |
Costs recovered from all users nationally, including the portion attributed to renewable-linked transmission and to high-voltage direct current (HVDC) links. |
|
Regional Component |
Costs recovered from users within a region. |
|
Transformers Component |
The cost of inter-connecting transformers. |
|
AC System Component |
The remaining alternating-current network, split into a usage-based part and a balance part. |
The users who pay are called designated ISTS customers. The charges fall mainly on drawee customers — distribution companies and large consumers who take electricity out of the network — largely in proportion to the network access they hold, with one part allocated by actual use of the network. The rates are computed monthly and published in rupees per megawatt per month.
Since 1 October 2023, the quantity that access is measured in has been set by the CERC (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022. General network access (GNA) is defined in those regulations simply as “open access to the ISTS granted under these regulations”. A distribution licensee or a bulk consumer connecting directly to the ISTS with a load of 50 MW and above can apply for it in its own right.
There are two routes, and most businesses sit on the first.
The state-level charges on the second route — wheeling, the surcharges, banking and standby — are a separate subject, set by your State Commission, and are covered in the open access guide in this series.
The ISTS waiver is a policy under which inter-state transmission charges are not levied on the power from qualifying renewable projects, for 25 years from commissioning. It began with Ministry of Power orders for solar in September 2016 and for wind in June 2017, and has been extended several times since. The key features are these:
The waiver has been one of the clearest examples of policy bridging today's energy needs with tomorrow's clean solutions: it lowered the cost of moving renewable power from the states best placed to generate it to the states where demand sits.
Rather than ending on a single date, the waiver steps down by a quarter each year for solar, wind and wind-solar hybrid projects. The schedule is now in CERC's regulations: Regulation 13 of the Sharing Regulations, as amended on 26 June 2025, sets it out by date of commercial operation.
|
Commercial operation date (solar, wind, hybrid) |
Share of ISTS charges waived |
Waiver period |
|
On or before 30 June 2025 |
100% |
25 years |
|
1 July 2025 – 30 June 2026 |
75% |
25 years |
|
1 July 2026 – 30 June 2027 |
50% |
25 years |
|
1 July 2027 – 30 June 2028 |
25% |
25 years |
|
After 30 June 2028 |
None |
— |
|
The live band, as at 30 September 2026: A solar, wind or hybrid project commissioned between 1 July 2026 and 30 June 2027 earns a 50 per cent waiver of ISTS charges for 25 years. The band moves to 25 per cent on 1 July 2027. |
Two points are commonly misread. The waiver is fixed by the commissioning date and then held for the full 25 years — a project that earned 100 per cent in 2025 keeps 100 per cent; it does not step down with the schedule. And the step-down applies only to projects still to be commissioned: those already running keep the band they earned for the rest of their 25 years.
Yes. Separate cut-off dates apply to other technologies, most of them for storage and for newer forms of clean energy:
|
Technology |
Current position |
|
Battery energy storage co-located with renewables |
100% waiver for 12 years for storage co-located at the same ISTS substation and charged from that renewable plant, commissioned by 30 June 2028. Other battery storage gets the same step-down by commissioning date as solar and wind, but for 12 years rather than 25. |
|
Pumped storage |
Waiver for 25 years from commissioning, where construction work is awarded by 30 June 2028. |
|
Green hydrogen and green ammonia |
Exemption for 25 years from commissioning, for plants commissioned by 31 December 2030. |
|
Offshore wind |
Complete waiver for 25 years for projects commissioned on or before 31 December 2032, stepping down to zero for projects commissioned after 31 December 2035. |
|
Hydro projects above 25 MW |
100% waiver for 18 years where both the PPA and the construction award are dated between 1 December 2022 and 30 June 2025, stepping down to 75, 50 and 25 per cent for later dates up to 30 June 2028. |
Two details matter most here. For battery energy storage, the co-located period is 12 years, not 25, under the regulations in force today. And for wind energy in India, the offshore schedule runs seven and a half years behind the onshore one: full waiver to 31 December 2032, reaching zero after 31 December 2035.
Two developments, and only one of them is in force.
Both sit alongside the Commission's wider work on connectivity for projects awaiting network capacity, including the Commission's one-time connectivity order of July 2026.
Transmission still has to be paid for. A waiver changes who pays, not whether the network's cost is recovered. CERC's minutes on the waiver, dated 31 May 2024, put it plainly: “Waived ISTS charges are required to be billed to the drawee DICs since the total ISTS Transmission charges of the ISTS licensees are to be recovered in full.”
The same minutes size the reallocation at roughly 7 per cent of the national monthly transmission charge in April 2024. That is a system-level figure — general market context, not a cost that applies to any one buyer.
On the other side of the ledger, the Ministry's April 2026 memorandum records that the benefit of the waiver accrues to procurers rather than to renewable developers, because procurers are the ones responsible for paying ISTS charges. That matters for anyone reading the waiver as a subsidy to independent power producers: as the Ministry frames it, the value flows to whoever buys the power.
The waiver's step-down is a policy working as designed: a published schedule, set years in advance, that lets the market plan around it. For the people reading it, a few practical points follow.
Transmission planning and network access are led by the transmission utilities and the Commission, and the waiver has been one of the tools that let India's renewable build-out grow faster than it otherwise could. As it tapers, the national task stays the same — navigating energy security while accelerating the low-carbon transition — with the cost of the network recovered from all its users on a common basis. For context on how procurement has adapted to date, see how utility renewable tenders have evolved.
Inter-State Transmission System. It is defined in Section 2(36) of the Electricity Act, 2003 and covers lines that carry electricity between states, across an intervening state, or within a state on a system built, owned, operated, maintained or controlled by the Central Transmission Utility.
ISTS carries power between states and is regulated by CERC. The intra-state transmission system (InSTS), largely owned and run by each State Transmission Utility, covers everything else, and its charges are set by each State Commission.
Yes, on a reducing scale. Solar, wind and hybrid projects commissioned between 1 July 2026 and 30 June 2027 get a 50 per cent waiver for 25 years. It falls to 25 per cent for projects commissioned from 1 July 2027 to 30 June 2028, and ends after that.
No. The Ministry of Power's order of 23 November 2021 limits the waiver to ISTS charges, not losses, except for projects whose bidding was completed by 15 January 2021.
Yes. The waiver covers solar and wind power that is self-consumed or sold to any entity through competitive bidding, a power exchange or a bilateral agreement, not only sales to distribution companies.
Under the regulations in force, battery storage co-located at the same ISTS substation as a renewable plant and charged from it gets a 100 per cent waiver for 12 years if commissioned by 30 June 2028. Other battery storage gets the same step-down by commissioning date as solar and wind, but for 12 years rather than 25.
Designated ISTS customers, mainly the distribution companies and bulk consumers who draw power from the network, largely in proportion to the network access they hold. CTUIL bills and collects the charges on behalf of the transmission licensees.
General Network Access — defined by CERC as open access to the ISTS granted under its 2022 connectivity and network access regulations, in effect since 1 October 2023. It is the quantity against which ISTS charges are now shared.